On July 11, China Hua Energy Group issued a notice on the purchase bidding notice for the 2020 photovoltaic component and reverser framework agreement. The scope of this framework agreement is the photovoltaic power generation photovoltaic components and reversers of the company’s region (industry) from July 2020 to June 2021.
According to the bidding notice, the bidding plan for photovoltaic components is divided into 4 bidding sections, purchasing voltage levels is 1500V photovoltaic components, with an estimated total procurement capacity of 5000MW, including a basic capacity of 4000MW and a reserve capacity of 1000MW.
The specific content of the component bidding is as follows:
<img src="http://img01.mybjx.net/news/UploadFile/202007/6373022705419125358689600.png" title="1.png" alt="1.png"//
This inverter bidding scheme is divided into 2 tags, with an estimated total procurement capacity of 5,000MW, including a basic capacity of 4,000MW and a reserve capacity of 1,000MW.
The specific content of the inverter bidding is as follows:

The following is the original text of the bidding:
China Hua Energy Group Co., Ltd.’s 2020 Photovoltaic Inverter Framework Agreement Procurement Tender Notice
(Tender number: HNNJ2020-07-BJGY-004)
1. Tender conditions
China Huaneng Group Co., Ltd.’s 2020 photovoltaic inverter has been approved for purchase. The project funds are owned by the company, and the bidder is China Huaneng Group Co., Ltd. This project has already met the bidding conditions and is now open for procurement of the 2020 Photovoltaic Inverter Framework Agreement by China Huaneng Group Co., Ltd.
2. Project Overview and Tender Scope
2.1 Scale: The scope of procurement of this framework agreement is the photovoltaic power generation project inverter of the company’s area (industry) from July 2020 to June 2021. The estimated total procurement capacity is 5000MW, with a base capacity of 4000MW and a reserve capacity of 1000MW. Basic capacity refers to the estimated capacity of the specific project target, and the reserve capacity refers to the capacity of newly added project during the useful period of the agreement. The final purchase volume is based on actual project requirements.
The framework agreement has a useful life of one year. During the useful life, when the actual capacity of each section of the framework agreement reaches the estimated procurement capacity, the bidder has the right to terminate or continue to execute the agreement early, and the bidder makes a commitment to this. If the project within each bid section fails to implement the department’s basic capacity and reserve capacity due to policies or current periods, the bidder does not undertake the actual procurement capacity to achieve the basic capacity and reserve capacity. The bidder must fully consider the risks and the bidder shall not assume any responsibility.
2.2 Segment Scheme: This inverter bidding scheme is divided into 2 marking segments, with an estimated total procurement capacity of 5000MW, including a basic capacity of 4000MW and a reserve capacity of 1000MW.
2.3 Delivery period: Delivery within 45 days after the contract is signed.
3. Investor qualification request
3.1 General qualification requirements
3.1.1 The investor is an independent enterprise legal person or other organization registered in the People’s Republic of China that complies with the laws. He has the ability to independently bear civil liability and has the right to independently entrust contracts;
3.1.2 The investor’s financial, credibility and other aspects shall have the following conditions:
(1) Not within the law of being held responsible for suspension of production, suspension of business or invasion of production, production operation is normal and contract performance is available;
(2) Not within the period of banning bidding as confirmed by the administrative department or the relevant documents of the China Energy Group Co., Ltd. system;
(3) No winning or serious violations have been obtained in the past three years, and no serious quality changes caused by the product recognized by the department;
(4) The list of trust enterprises has not been listed by the Political Manager of the Industrial and Commercial Bank of China in the national enterprise trust information disclosure system;
(5) The list of trust enterprises has not been listed by the Supreme People’s Court on the “Credit China” website (www.creditchina.gov.cn) or various trust information sharing platforms;
(6) The legal representative or unit responsible person is a one-person two or more legal persons, the parent company, the full-funded subsidiary and its holding company shall not unintentionally extend the bid to the male supporting role Xie Xi who is trampled by the male protagonist and stolen on stone in a unified bidding project or a certain unplanned subdivision.
3.1.3 This project does not allow joint bids.
3.1.4 This project receives representative merchant bids.
If the bidder is a representative, he shall provide authorization for this project issued by the manufacturer of the invested equipment (requesting to obtain the manufacturer or the general representative of the country for imported equipment). If the equipment manufacturer and its representatives trade the bid documents at the same time, they will only receive the bid documents from the manufacturer; if two or more sales representatives trade the bid documents at the same time, and two or more have useful authorizations, all bids will be denied.
3.1.5 All potential bidders can purchase the department or all bidding documents of this bidding and participate in the bidding.
3.2 Special qualification conditions
3.2.1 The bidder’s bidding product shall have a product certification book issued by a nationally recognized certification body.
3.2.2 The products that the bidder bid shall be certified by one of CGC, CQC, and TUV.
3.2.3 The products invested by the bidder shall meet the relevant provisions of the “Photovoltaic Manufacturing Industry Standards (2018 Edition)”.
3.2.4 Supply performance:
Serial series inverter segment: The bidder or the manufacturer representing the bidder brand has a cumulative shipment of 50kW and above 50kW and above since January 1, 2017, with a perfect after-sales service system.
Centralized inverter tag segment: The bidder or the manufacturer representing the bidder brand has a cumulative shipment of 2.0MW and above 2017 to more than 1 million kilowatts, with a perfect after-sales service system.
3.2.5 The bidder needs to supply the sales performance related certificates of the manufacturer he or he represents to the manufacturer (project name, contract cover, sign page, supply range page, etc.)
4. Acquisition of bid documents
The acquisition time: from 00:00 on July 12, 2020 to 17:00 on July 17, 2020.
How to get it: Log in to China and have a chance to rest. During her nap, she had a dream. Huaneng Group E-commerce Platform (http://ec.chng.com.cn) registration (for registration, you only need to upload the bidding documents fee and exchange base). After the registration is passed, the potential bidder downloads the bid documents during the sale period after the bidding representative organization is reviewed and approved by the bid representative organization. The bidding document fee is RMB 3,000 per section per package. Except for the bidder or bidding agency, no refund will be made once the bidding documents are sold.
Opening unit: Huaneng Power Road and Resources Holdings Co., Ltd.
Opening bank: Beijing Guozhan Branch, Guangzhou Bank Co., Ltd.
Opening bank Number: 6232593799002480062
Note: The bidding document fee must be transferred by the bidder account at one time to the designated account of the bidding agency (the time of arrival is based on the entry account issued by the bank). Please indicate the bidding number + unit name when transferring the payment, so that it can be checked and verified.
Contact: The contact person who potential bidder fills in the bidding file page must fill in the business contact person who writes this bid. The notices of the bidding period and other periods will be sent to the contact person’s mobile_phone by text message.
5. Deadline for delivery of bid documents
5.1 Deadline for delivery: 10:00 on August 3, 2020
5.2Submission method: Upload documents from China Huaneng Group Co., Ltd. e-commerce platform (http://ec.chng.com.cn).
6. Opening time and location
Opening time: 10:00 on August 3, 2020
Opening location: China Huaneng Group Co., Ltd. E-commerce Platform (http://ec.chng.com.cn). After the opening time, the purchasing representative agency clicks the bidding file on the Huaneng Group E-commerce Platform to start the decryption button, and each bidder decrypts their bidding files online. The process is recorded in the file for verification.
7. Others
7.1 Preface to issuing bid notices.
This notice was issued on the China Tendering and Tendering Public Service Platform (http://www.cebpubservice.coSugar daddym/), and the China Huan Energy Group Co., Ltd. e-commerce platform (http://ec.chng.com.cn).
7.2 Registration and login
7.2.1. This project is used to register, TC: